Working timeline
Plan in phases, with time for decisions.
These are planning ranges rather than promises. Address, scope, design completeness, review agencies, procurement and concealed conditions all affect the actual schedule.
6–12+ weeksDesign and selections
Layout, cabinet design, appliance specifications, structural review and finish selections should be substantially coordinated before ordering.
4–12+ weeksPermits and procurement
Permit review can run while cabinetry, windows or long-lead equipment are released once dimensions are verified.
10–20+ weeksConstruction
Demolition and rough work are followed by inspections, wall close-up, cabinetry, counters, finish trades, appliance installation and final checks.